According to documents from USAID, 750 houses built by USAID near the new Caracol industrial park, were found to be of poor quality and will take millions of dollars to repair.
According to documents from USAID, 750 houses built by USAID near the new Caracol industrial park, were found to be of poor quality and will take millions of dollars to repair. The houses are part of USAID’s “New Settlement Program,” which was the subject of a Government Accountability Office (GAO) report in October 2013 as well as a USAID Inspector General (IG) audit in April 2014.
The GAO report found that USAID had initially planned on building 15,000 houses but that the number had been reduced to just 2,600. At the same time costs skyrocketed, from $53 million to over $90 million. At the time of the report, just 900 houses had been built across Haiti. (For more on the housing project, and how these estimates changed, see “Outsourcing Haiti” from earlier this year in Boston Review.)